它始于您的日历分配。use a project calendar and change your time time setting to suit, i.e. hours per day, hours per week, hours per month, hours per year.... the reason you are experiencing different time per activity level is because primavera is calculating it at your default calendar (customarily at 8hrs/day) where in fact you changed it to 10hrs/day (which is your project calendar).